ACS Wire Center Remodel Anchorage, Alaska
- $300K project with 8 week timeframe
- Replacement of approximately 70 tons of cooling equipment, including two 30 ton Liebert DS units with Dry Coolers and three 3 ton Mitsubishi split systems
- Project consisted of craning old units from a three story building and reclaiming refrigerants for disposal
|
|
|
Alaska Geologic Materials Center Anchorage, Alaska
- $607K project with 6 month timeframe
- Remodel of approximately 94,000 sq. ft building with installation of new plumbing including acid waste fixtures, new boilers, two 1.2 million BTU RTU units, medium pressure welded gas systems, and HVAC controls throughout
|
First American Baptist Church Anchorage, Alaska
- $48K project with 2 week timeframe
- Demolition and replacement of 2 existing cast iron boilers in two different boiler rooms into one high efficiency condensing boiler room, resulting in extensive cost and energy savings
- Converted the existing pneumatic controls to a new 24 volt control system
- Provided combustion analyzation and start-up procedures on condensing boilers
|
|
|
Wasilla City Center Phase IV Wasilla, Alaska
- $210K project with 3 month timeframe
- New construction project of 12,000 sq. ft office complex consisting of underground waste and vent piping, overhead gas piping, new bathrooms, RTU’s (3 and 6 ton), roof drains and rain leader piping, HVAC balancing and controls
|
Southcentral Foundation Office Remodel Anchorage, Alaska
- $175K project with 4 week timeframe
- Remodel of approximately 20,000 sq. ft. office building with replacement of existing 25 ton packaged rooftop unit with duct modifications and control upgrades
- Project included craning equipment off and on 3-story roof
|
|
|
Turnagain School Anchorage, Alaska
- $164K project with 8 week timeframe
- Demolition, removal and replacement of existing galvanized/copper domestic cold/hot water piping systems throughout the school to new CPVC plastic pipe
- Use of commercial rated Pex tubing throughout the project
- Project included snaking through tight spaces of walls and corridors
|
Pyramid Water Treatment Plant Upgrade Unalaska, Alaska
- $1.03 Million project with 1.5 year timeframe
- New construction project consisting of plumbing, oil fired boilers, fuel oil tank and containment underground fuel oil piping, trench drains, HVAC systems and controls
|
Y-K Correctional Water Tank Upgrade Bethel, Alaska
- $72K project with 6 week timeframe
- Project included piping, valves, flushing and chlorination of new domestic water storage tank located at the correctional facility
|